The machine was fully stripped and rewound with a full, resin-rich, coil system, and each coil was tested to withstand 14,200 Volts to earth, and between phases.
With the addition of a double flood varnishing process, the motor windings are superbly protected against external contaminants while remaining flexible enough to cope with the rigorous demands on a motor that is housed in a cold and damp environment.
The winding process was completed in 7 working weeks, delivering a more cost-effective solution to replacing the machine, which would not only be much more expensive, but also have a 20 week lead time.
This Project was delivered in-line with our commitments to Health and Safety, Quality and the Environment through our ISO Management Systems.