The works included the installation of two 11kv – 433v transformers and all associated LV and HV switchgear and cabling for both the CHP3 and CHP4 installations and the Puregas plant on site. GES also designed and installed two bespoke containerised substations, one LV and one HV, to meet the need for rapid turnaround and to comply with the connection agreement from the DNO.
This Project was delivered in-line with our commitments to Health and Safety, Quality, and the Environment, with all installations tested and commissioned to GES Procedures, which meet the highest Industry standards, and comply with our NQA-accredited ISO Management Systems (14001, 9001, and 18001). Full RAMS were made available to the client.